Excom-Siroco Planning: Implementation of the hydraulic short circuit in turbine/pumping units

J. García-González A.F. Oviedo-Gómez

April 2024 - June 2024

Funding entity Endesa Medios y Sistemas S.L


The general objective of the project is to make the necessary developments so that the production version of the Excom-Siroco Planning model (ExSp) allows the consideration of the hydraulic short circuit in turbine-pumping groups equipped for it.


Layman's summary: This project is part of the developments of the Excom-Siroco Planning (ExSP) model, which allows for the planning of the operation of the entire generation portfolio of Endesa in the Iberian Peninsula, taking into account both the energy market and the secondary regulation reserve market. The generation units are modeled with a high level of detail (thermal group and hydraulic turbine) in a coordinated manner with the other models developed by the same IIT team (EXCOM and EXLA models).



2024_EXSP_Cortocircuito_Hid